Ridley Agri Products, Colac, VIC

Summary

Mechanical & Electrical Decommission of Stock Feed Plant in Rural Victoria.

Started : July 2008
Completion : August 2008

Scope

Mechanical & Electrical Decommission of Entire Stock Feed Manufacturing Site:

  • Electrically disconnecting & removal of all wiring inclusive of control systems
  • Mechanical removal of plant items being relocated to another site
  • Cataloguing of all equipment removed
  • Demolition of site Silos & Ridley Building Internals
  • Civil Work Remediation
  • Roof Plumbing Remediation
  • Fully ATIVO Managed & Supervised Project

Outcome

  • Zero LTI’s or quality defects
  • Completed all site works with no variations, Fixed Price Quoted.
  • Completed Project on budget & within the Client’s timeframe