Cummins Power Station – Hunter Valley NSW
Project
Mechanical Installation of the 29MW Power Station
Kurri Kurri , Hunter Valley NSW
2006
Scope
This project consisted of the mechanical installation of the 29MW Power Station. The scope of work comprised of the provision of all supervision, labour, equipment, and consumables to perform Piping Erection and Associated Mechanical Equipment Installation Works.
Tasks undertaken:
- Greenfield site
- Installation of Coolant pipe work
- Installation of Radiator equipment installation
- Installation of Fuel pipe work
- Installation of Urea Dosing system pipe work and associated mechanical equipment installation
- General pipe welding
Crew
ATIVO Services: 10 people
Managed Sub-contractors: 2 people